C/o
6Nos Duplex Type T-V Qtrs. at 10, Strand Road, Patna
(Shifted
to 38 Harding Road ,Patna as 7Nos. T-V Qtrs. in One Block)
|
|
Salient Features
|
| 1. |
Plinth Area of the Bldg. |
1560.00 Sqm. |
| 2. |
Estimated Cost put to Tender |
Rs 89,35,866/-. |
| 3. |
Tendered Amount |
Rs 1,00,19,252=50. |
| 4. |
Time |
17(Seventeen) months. |
| 5. |
Agency |
M/s Satyendra Kumar & Company. |
| 6. |
Agreement No |
128/EE/PTCD/2000-2001 |
| 7. |
Clause 12 of the Agreement |
12.12% above (DSR'97). |
| 8. |
Date of start as per Agrt. |
10.01.2001 |
| 9. |
Date of stipulated completion |
09.06.2002 |
| 10. |
Date of actual completion |
31.08.2003 |
| 11. |
A/A & E/S Amount |
Rs. 1,38,29,800 |
| 12. |
Provision of Civil works in P/E |
Rs. 1,35,01,800 |
| 13. |
Provision of Electrical works in P/E |
Rs. 4,28,000 |
| 14. |
Total Expenditure |
Rs. 94,50,000
|
|
C/o Administrative
Building at C.T.O. Compd, Patna (SH:Superstructure)
|
|
Salient
Features
|
| 1. |
Plinth Area of the Bldg |
6349.00 Sqm |
| 2. |
Estimated Cost put to Tender |
Rs. 3,16,09,189 |
| 3. |
Tendered Amount |
Rs.3,28,48,493 |
| 4. |
Time |
36(Thirty six) months |
| 5. |
Agency |
M/s Satyendra kumar & company |
| 6. |
Agreement No |
32/EE/PTCD/2001-2002 |
| 7. |
Date of start (as per Agrt) |
12.06.2001 |
| 8. |
Date of Stipulated Completion |
11.06.2004 |
| 9. |
A/A & E/S Amount |
Rs.8,34,24,300 |
| 10. |
Prevision of civil works in P/E |
Rs.6,08,38,960 |
| 11. |
Provision of Electrical works in P/E |
Rs.2,25,85,340 |
| 12. |
Clause 12 of the Agreement |
3.92% above (DSR'97) |
| 13. |
Uptodate Expenditure (till date) |
Rs.2,00,00,000 |
| 14. |
Cost of Foundation (Seperate Agreement) |
Rs.66,60,000 |
|
C/o
9Nos T-V Qtrs at 40, Harding road, Patna (2 Nos. V/E and 7 Nos.
in separate block).
|
|
Salient Features
|
| 1. |
Plinth Area of the Bldg. |
2010.00 Sqm. |
| 2. |
Estimated Cost put to Tender |
Rs 1,00,66,550. |
| 3. |
Tendered Amount |
Rs 1,07,58,518. |
| 4. |
Time |
15(Seventeen) months. |
| 5. |
Agency |
M/s Satyendra Kumar & Company. |
| 6. |
Agreement No |
127/EE/PTCD/2000-2001 |
| 7. |
Clause 12 of the Agreement |
6.87% above (DSR'97). |
| 8. |
Date of start as per Agrt. |
10.01.2001 |
| 9. |
Date of stipulated completion |
09.04.2002 |
| 10. |
Date of actual completion |
30.09.2003 |
| 11. |
A/A & E/S Amount |
Rs 1,30,44,000. |
| 12. |
Provision of Civil works in P/E |
Rs 1,23,21,400. |
| 13. |
Provision of Electrical works in P/E |
Rs 7,22,600. |
| 14. |
Total Expenditure |
Rs 1,05,00,000
|
|
TELECOM INSPECTION QUARTER
AT BUDH MARG, PATNA
|
| It is situated
at the Centre of main heart of the Patna, capital
of Bihar , along the peripheral of the site Gandhi Maidan, Maurya
lock (Modern marketing complex), Musium, Planetoriam, Railway
station , Bus stand situated within a radius of nearly one Km.
This building is constructed infront of famous Sinha Library in
Budh Marg Road which is inter-connected from Bailley Road to Gandhi
Maidan. |
|
Salient Feature of
the Building
| 1. |
Name of Project
|
C/o Telecom, Inspection Qtrs, at Budh
Marg, Patna
|
| 2. |
Name of Agency
|
M/s Raj Construction
|
| 3. |
Agreement No
|
218/EE/PTCD/2001-2002
|
| 4. |
Date of Start
|
26.09.2002
|
| 5. |
Tentative target date of completion
|
15.10.2004
|
| 6. |
Estimated Cost
|
Rs.61,15,283
|
| 7. |
Tender Amount
|
Rs.78,31,735
|
| 8. |
A/A & E/S
|
Rs.1,00,87,000
|
| 9. |
Clause 12
|
DSR'97 + 28.07% Above
|
| 10. |
Purpose
|
Since there is no any Independent inspection
Qtrs. in Bihar Telecome, circle. Therefore it is requirted
to construct a fully independent Qtrs, in peacefully resident
area.
|
| 11. |
Plinth Area
|
415Sqm
|
| 12. |
Storey
|
At Present G + 1 & one more floor
as vertical extension in future.
|
| 13. |
Suit
|
At present 09(nine) Nos. of suit to be
constructed along with one small suit for care taker.
|
| 14. |
Type of Construction |
R.C.C framed structure |
| 15. |
Type of Soil |
Black cotton soil having bearing capacity
10 tone at depth of 2m |
| 16. |
Mix |
M20 |
| 17. |
Design |
Based on latest version of standard Pre. with
most economical |
| 18. |
Estimate |
Based on DSR'97 |
| 19. |
Present Activity |
Ground floor roof casting is on going , half
portion roof has been already casted. Column raising of
Ist floor roof is also going on. |
|
|
T.E BUILDING AT PATNA
CITY (PHASE-I)
|
| It is situated in main commercial area (One of the
most important telecom, revenue collection centre) of Patna.This
is located near Gurudwara at main road of Patna city.In the periphery
of the building, mainy commercial complex of whole saler shope
and railway station is situated within the one Km. of radius.
This locality is most busy place of Patna city. |
|
Salient Features
|
| 1 |
Name of Project
|
C/o T.E.Building Patna city (Phase-I) |
| 2 |
Name of Agency
|
Sri Kameshwar Prasad Singh |
| 3 |
Agreement No
|
130/EE/PTCD/2000-2001 |
| 4 |
Date of Start
|
10.05.2003 |
| 5 |
Tentative target date of completion
|
31.05.2004 |
| 6 |
Estimated Cost
|
Rs.26,31,721 |
| 7 |
Tender Amount
|
Rs.34,76,880 |
| 8 |
A/A & E/S
|
Rs.54,27,500 |
| 9 |
Clause 12
|
DSR'97 + 32.11% Above |
| 10 |
Purpose
|
As this is most revenue telecom, collection sentre
in Patna. Hence to provide bettre service to subscriber, there
required new exchange with new technology. At Present vary old
X'ge is working.Due to large telidensity , there require new telephone
X'ge of new telephone X'ge building to be constructed to full
fill the desire requirement |
| 11 |
Plinth Area
|
142 Sqm |
| 12 |
Storey
|
At present G + 2 |
| 13 |
Type of Construction
|
R.C.C. FRAMED STRUCTURE |
| 14 |
Type of Soil |
Black - culton soil |
| 15 |
Mix |
M2O |
|
Difficulties during Construction
|
|
This site is very conjusted , there is no space to dumping
building material like sand, aggrigates, steel etc. The materials
are damped in police station campus on request. At first the
site was fully engaged (dampped) with telephone materials like
pole, damage old batteries charger etc. It was cleaned and shifted
to other places by agency. During the piling work some any obstacles
appears like surang, well, earthing cable( plates),stone slab,old
brick wall, boulder etc. below ground which cause the delay
of works (shown in photograph). The soil , Which also creates
problem in piling works.
Position of Works:- Most of pile has been casted
except problamatic pile due to well and muddy soil . The work
is fully stoped due to revise structural design of pile cap
and remaining revise pile design.
|
|